Emergency Response Archives - The Dutra Group https://www.dutragroup.com/portfolio-tag/emergency-response/ The Dutra Group Website Sat, 05 Apr 2025 16:34:00 +0000 en-US hourly 1 https://wordpress.org/?v=6.9.1 https://www.dutragroup.com/wp-content/uploads/2022/09/cropped-dutra-logo1-512x512-1-32x32.png Emergency Response Archives - The Dutra Group https://www.dutragroup.com/portfolio-tag/emergency-response/ 32 32 Tyler Island, California, Emergency Levee Repair https://www.dutragroup.com/portfolio-item/tyler-island-emergency-levee-repair-2/ https://www.dutragroup.com/portfolio-item/tyler-island-emergency-levee-repair-2/#respond Sun, 03 Dec 2017 20:32:59 +0000 https://www.dutragroup.com/?post_type=portfolio-item&p=12311 We immediately responded to a saturated levee emergency and repaired a slope damaged by heavy rains.

The post Tyler Island, California, Emergency Levee Repair appeared first on The Dutra Group.

]]>

Project Description

In side slope failure, due to saturated Levee slope from heavy rains, leaving a 10’ wide water side portion of Levee standing against an already high water elevation and heavy flows due to extreme run off. Dutra was call for an immediate emergency response to rebuild the Levee section before it failed and created a breach in the Levee, flooding the Island and parts of Walnut Grove.

Major Challenges

This project was unique compared to other projects in the fact that it was an immediate response emergency call out to save the Levee section, prevent a Levee breach and to provide safety to the public and homes in the area. The Dutra Group was called by the District Engineer on 2/13/2017 at 1000 hrs. The Dutra Group had a Crane barge, loaded rock barge with tug on site placing rock as directed by 1130 hrs. the same day.

Also, there was mobilized within 2 hrs., assist equipment, 2 dozers, 416 back hoe, 84” pad foot compactor, porta potties, and light plants with supervisors and employees to operate at a 24-hr. basis. The Derrick Barge 24 was also mobilized out of Dutra Rio Vista facility to assist. Under direction of the district there was placed 9,024 tons of rock product placed brought from Dutra’s San Rafael Rock Quarry by barge and tug 65 Nautical Miles away.

In addition, with that 8,182 tons of fill was placed and brought by barge and tug from Decker Island 20 nautical Miles away. 2 tug boats were used on project and coordinated with Caltrans and the Mokelumne River bridge openings.

Project was completed on 2/16/2017 4 days later with no safety incidents.

The post Tyler Island, California, Emergency Levee Repair appeared first on The Dutra Group.

]]>
https://www.dutragroup.com/portfolio-item/tyler-island-emergency-levee-repair-2/feed/ 0
2004 Jones Tract Levee, California, Emergency Breach Repair https://www.dutragroup.com/portfolio-item/jones-tract-flood-2/ https://www.dutragroup.com/portfolio-item/jones-tract-flood-2/#respond Wed, 01 Dec 2004 20:41:58 +0000 https://www.dutragroup.com/?post_type=portfolio-item&p=12318 After a handshake deal with the governor, we plugged the breach with 200,000+ tons of rock, finishing 20 days early.

The post 2004 Jones Tract Levee, California, Emergency Breach Repair appeared first on The Dutra Group.

]]>

Project Description

On June 3, 2004, at approximately 7:50 a.m. a levee breach occurred on the west levee of the Upper Jones Tract in the southern region of the Delta in San Joaquin County.

The break occurred approximately 1/4 mile north of the Woodward Island ferry exposing the tract to flooding from Middle River. Governor Arnold Schwarzenegger declared a State of Emergency and Dutra Construction was hired to close the breach. Dutra Construction completed closing the breach on June 30, 2004, approximately

20 days ahead of schedule. The closure occurred several days before an astronomical high tide was due. This high tide would have resulted in a rise of the island water surface elevation to its highest level since the day of the breach. As a result of the closure and completion of the protection efforts, there were no problems due to the high tidal period or winds.