Moss Landing

Project:  Moss Landing Harbor, Parking Area, Boat Launch Ramp

Shore Protection Wharf and Dock

Owner: Moss Landing Harbor District

Project Value: $3,450,803

Project Duration: Sep 2005 ~ Feb 2007

Purpose: Upgrade the Moss Landing Harbor area

Construction Activities:

  • Demolition and removal of existing timber piles, concrete
    rubble, debris and timber logs
  • Grading, paving and striping of approx. 3.5 acres of existing parking area
  • Provide a boat washdown facility, including all utility hookups; provide storm drain system with pre-fabricated water treatment units
  • Dredging and disposal of non-hazardous material; contruction for a four-lane boat launch ramp using cast-in place reinforced concrete slab, precast concrete panels, articulated boarding floats, pile guides, metal connectors and framing, stanchions, rub rail, cleats, rub strip and all other auxiliary items
  • Provide precast, prestressed concrete guide piles for Boarding Floats
  • Furnish and place sand fill material
  • Provide rock riprap material for approximately 1000 linear feet of shore protection
  • Provide precast, prestressed concrete piling for wharf and access platform
  • Provide cast-in-place, reinforced concrete pile caps, beams and topping for wharf and access platform
  • Provide precast, prestressed deck slab planks for wharf and access platform
  • Provide metal railing with mesh for wharf and access platform; provide precast prestressed concrete guide piles for dock
  • Furnish and install concrete floating system including pile guide frames, pile guide roller assembly and mooring hardware
  • Furnish and install electrical equipment for dock
  • Design, furnish and install aluminum gangway
  • Remove all debris from site and leave in clean condition; perform other requirements as specified in the contract documents

 

 